Second electricity cable could be running by 2030

BBC A drone shot of houses in GuernseyBBC
About 90% of Guernsey's power is imported from France through an undersea cable

A second under-sea electricity cable could be up and running by 2030 in Guernsey under plans being put forward by two of the island's States committees.

The cable would provide a new link to import electricity from France either as a direct connection or via Jersey. It is expected to cost between £113m and £209m.

However States members will be asked by Guernsey's Environment & Infrastructure Committee (E&I) and the States Trading Supervisory Board (STSB) to approve a larger budget of up to £253m as a "prudent approach" while final costs are figured out.

STSB president Mark Helyar said the scheme would require "significant expenditure" but said doing nothing was not a realistic option.

Guernsey Electricity said customers could face above-inflation increases until about 2036 to pay for the investment but over 30 years bills are expected to rise by less than inflation overall.

Guernsey currently imports 90% of its electricity through an undersea cable called GJ1.

The power, which comes from France in a deal with the Channel Islands' governments have with French power provider EDF, is routed through Jersey and into Guernsey from Havelet Bay.

When the Electricity Strategy was agreed in 2023, it was believed a new inter-connector would be a direct link to France.

However, Guernsey Electricity has since found having a second cable to the continent via Jersey would deliver the same benefit, but a policy letter does not make any recommendation on the route the cable takes.

A graph showing the inter connectors from France to Jersey and onto Guernsey.
The GJ1 cable was installed in 2000

E&I president Adrian Gabriel said the second connection would improve security and resilience.

"[It will] provide greater energy independence, deliver best value for customers, enable appropriate competition and consumer choice, and minimise environmental impact from on-island power generation."

The proposals are due to be debated by politicians in December.

Correction 10 November 2026: A previous version of this article stated that States committees anticipated a second cable would come directly from France. It has been updated to reflect the latest position of Guernsey Electricity which now believes a cable to the continent could be routed via Jersey for the same benefit.

Follow BBC Guernsey on X, Facebook and Instagram. Send your story ideas to channel.islands@bbc.co.uk.