HSE 'working urgently' on building collapse clean-up

BBC Red barriers across a road with a police road closed sign.  It is a sunny day.BBC
Cherwell Street in Banbury has been partially closed since the collapse on 21 October

The Health and Safety Executive (HSE) has said it is "working urgently" to help make the site of a partial building collapse safe.

An apartment block under construction on the A4260 Cherwell Street in Banbury partly collapsed alongside scaffolding on 21 October, closing the road for nine days.

The road has since been partially reopened, but local councillor Paul Austin Sargent accused the HSE of "holding the town to ransom" over delays related to the clear-up of the site.

Responding, a HSE spokesperson said it was "working urgently with the contractors on site as they seek to make it safe".

"The road closure is a matter for the local council, who have been in contact with councillors and members of the community," the spokesperson said.

"We realise this is a difficult situation for residents and businesses in the area."

Paul-Austin Sargent Local councillor Paul-Austin Sargent is holding a sign saying "HSE: STOP HOLDING BANBURY TO RANSOM!". He is standing in front of the building site collapse on Cherwell Street.Paul-Austin Sargent
Local councillor Paul-Austin Sargent has accused the Health and Safety Executive of "holding the town to ransom"

On Wednesday, Cherwell District Council said its inspectors had found the building presented a "significant risk of further structural failure".

It said a nearby garage had been warned about the situation and advised to close immediately, while local residents were told to remove cars parked nearby.

The road was temporarily closed on Tuesday and Wednesday to install fencing along the route, which the council said would "mitigate the risk of falling debris".

It reopened on Thursday to traffic in both directions, after it was closed northbound last week due to congestion concerns.

Banburyshire Info Police cars parked on Cherwell Street in front of a police cordon. There are other emergency service teams in the distance. On the left is the new building - which is surrounded by scaffolding.Banburyshire Info
Two people were injured and taken to hospital following the collapse

The active lanes are the two furthest from the collapse site - with the council saying those closer to the incident could only reopen once it had been made safe.

"Our focus now is on working with the developer to ensure the site is made safe and normal access to Cherwell Street can be restored as quickly as possible," said Chris Aramini-Brant, the authority's planning and enforcement chief.

The collapse on Cherwell Street took place near to its junction with Bridge Street, which is one of the north Oxfordshire market town's busiest crossroads.

Thames Valley Police said nine workers were at the building site when the collapse happened, with two taken to hospital due to their injuries.