First sections of £8.3m footbridge arrive in city
Peterborough City CouncilThe first sections of a new £8.3m footbridge have arrived in Peterborough, as installation work begins.
Three deck sections for Cygnet Bridge have been delivered to the city this week by wide-load convoy, under police escort, and will be lifted into place in the coming days alongside the bridge's mast.
Part of the River Nene has been temporarily closed until 24 December to allow the work to be carried out safely.
Peterborough City Council said the bridge would create a more direct route for pedestrians and cyclists between Fletton Quays, the Embankment and the city centre.
Peterborough City CouncilA 700-tonne crawler crane, believed to be one of the largest currently operating in the UK, has been assembled on site to lift the bridge sections into position, the local authority said.
Preparatory works began in May and included the creation of a construction compound and welfare facilities.
A spokesperson for the council said the project had faced challenges, including summer heatwaves and difficult ground conditions, but work had remained on schedule.
The construction of the bridge is expected to finish by spring next year.
Peterborough City CouncilThe project is being funded by the Cambridgeshire and Peterborough Combined Authority, the government's Towns Fund and Peterborough City Council.
The scheme's cost increased from an original estimate of £6.3m to £8.3m following design changes and rising costs linked to sewer diversion works.
Under the revised funding package, the Towns Fund is contributing £2m and the combined authority £5.4m, with the remainder coming from the council's redevelopment budget.
Peterborough City CouncilDo you have a story suggestion for Peterborough? Contact us below.
Follow Peterborough news on BBC Sounds, Facebook, Instagram and X.