Somerset Council An aerial view of work on the new roundabout.  There are various construction vehicles and the roundabout is surrounded by fields and trees.Somerset Council
The new roundabout near Wells is being built in a bid to improve road safety

A £4m project to build a roundabout at a crash-prone junction is expected to be completed next month, a council has said.

Somerset Council said the Whitnell Corner junction on the B3139 Bath Road, near Wells, had been the scene of 67 collisions in the past 20 years.

The work is scheduled for completion between 11 and 18 December.

Councillor Richard Wilkins said work was "progressing really well" and the council expected the roundabout to "open to traffic on time".

There were 22 collisions at the junction, three of which were serious and one fatal, between 2019 and 2024.

Somerset Council said the roundabout would provide the safety improvements needed as well as a permanent solution that does not rely on technology.

Contractor Octavius began work on the project in July and the road has been closed to traffic since then.

The roundabout will have a 40mph speed limit introduced on all the approaches.

Somerset Council A few cars getting ready to drive through a cross roads. There are fields all around the roads. It is an overcast and grey day.Somerset Council
The Whitnell Corner junction pictured before work on the new roundabout began

The council said construction of the central island was complete with the surfacing of the roundabout the next step.

"Obviously, with the road being closed for such a period of time, it has been disruptive," said Wilkins.

"It's worth pointing out that the community have longed shared our concerns about this junction so it's really great that we are getting the work done."