Getty ImagesThe projected cost of creating specialist primary school spaces in Barnsley has more than doubled to almost £7.4m.
Space at The Mill at Worsbrough Bridge is set to be converted to provide 40 places for children with special educational needs and disabilities, helping more pupils learn closer to home.
Children are expected to start at the school in September 2028 but a council report said the refurbishment was more extensive than originally anticipated.
Barnsley Council plans to convert an empty building to provide specialist support for pupils who are on the autism spectrum and have communication needs.
A local authority report said surveys and design work revealed more extensive refurbishment, access works and specialist equipment requirements were required, pushing the total budget up from just under £3m.
Building works and specialist fit-out costs have risen from £1.8m to £3.6m, while the estimated cost of a new site entrance and vehicle access route has risen from £320,000 to £760,000.
Fees, overheads, risk and contingency allowances now total £2.34m, compared with £420,000 previously.
Officers describe the overall figure as a cautious estimate rather than a final construction price.
The project would be paid for entirely through a ring-fenced government grant, without additional council borrowing, according to the Local Democracy Reporting Service.
'More specialist education'
The counil's Cabinet agreed in February to accept £9.4m to create and improve SEND and alternative provision across Barnsley.
Waterton Academy Trust is the preferred partner to run the school. Temporary provision at Kings Oak offers up to 20 places while The Mill progresses.
Councillor Gary Hall, cabinet spokesperson for children's services, said: "These proposals would help us create more specialist primary school places locally, so more children with SEND can learn closer to home.
"The Mill would make good use of an existing council-owned site and help us provide more specialist education places here in Barnsley, reducing the need for children to travel outside the borough for their education."
Officers estimate that, once full, the school could reduce annual placement and transport costs by £1.6m compared with equivalent independent and out-of-borough provision.
They said that refurbishing The Mill remained the most deliverable option.
Barnsley Council's cabinet will consider the revised budget on Wednesday, October 7.