Upgraded West Highland Line reopens with £9m Kyle project to follow

Network Rail An aerial view of the West Highland Line with a viaduct over a stretch of land and water leading into a tunnelNetwork Rail
Various sections of the West Highland Line have been improved

The West Highland Line has been reopened following the completion of a nine-day £13m upgrade.

The scenic railway line, linking Glasgow to destinations including Oban and Mallaig, features the famous Glenfinnan Viaduct seen in the Harry Potter films.

Network Rail carried out work at locations between Helensburgh, Fort William and Mallaig.

It is now preparing for a £9m project at Inverness station and along the Kyle line, with services between Inverness, Dingwall and Kyle of Lochalsh affected for three weeks from 28 November.

The West Highland Line project involved renewing more than 2.5 miles (4km) of worn track at locations between Helensburgh and Mallaig, including in tunnels at Loch nan Uamh and Beasdale.

Work was also done to drainage and culverts, including between Glen Douglas and Arrochar and Tarbet, to improve flood prevention measures.

What is planned for Inverness and the Kyle line?

Getty Images An aerial view of Inverness Station showing the roofs of the platforms and tracks emerging from the station. Around the station are the densely built-up areas of Inverness city centre, including the Eastgate Shopping Centre and parts of the wider city beyond.Getty Images
Improvements are planned for platforms at Inverness Station

Network Rail said its upcoming £9m project would make the Kyle line "safe and reliable".

The closure will run from 28 November to 18 December, with services between Dingwall and Kyle of Lochalsh resuming on 19 December.

Network Rail said it was working with ScotRail to support passengers during the suspension of train services.

Replacement buses will run between Inverness and Dingwall, with amended train services running from Dingwall to Invergordon, Tain, Thurso and Wick.

Passengers have been advised to plan ahead and check before travelling.

During the three-week closure a range of renewals, repairs and other maintenance work is to take place.

At Inverness Station, engineers will renew track and sleepers at platforms five and six. Equipment that allows trains to move between different tracks will also be refurbished.

About four miles (7km) of track will be renewed at several locations, including between Welsh's Bridge and Rose Street level crossing in Inverness, Achanalt and Rosebank near Achnasheen, and between Strathcarron and Stromeferry.

Several drains between Dingwall, Achnasheen and Stromeferry will be renewed, and structural repairs and track renewal work done to multiple railway bridges.

Gary Hopkirk, route director at Network Rail Scotland, said: "The Kyle line is an important connection for communities and the many visitors who use it each year, so we know there is never an ideal time to close it."