Menai Bridge repairs delayed by a further six months

BBC Photo of the Menai suspension bridge, with the water of the Menai Strait below and mountains behind.  The scaffolding used by workers to paint beneath the bridge can be seen, hanging from the deck.BBC
The historic bridge is a key link between the Isle of Anglesey and the rest of Wales

Work on one of the two bridges linking Anglesey to the rest of Wales has been delayed by a further six months.

Drivers crossing the 200-year-old Menai suspension bridge have endured delays, weight restrictions and closures for more than four years.

The latest delay to the repair and refurbishment works has been caused by the discovery of damp underneath the road deck, which is preventing it from being painted.

UK Highways A55 Ltd, which is in charge of maintaining the bridge, said it hoped to keep any further disruption to a minimum while it completes the refurbishment.

The Menai suspension bridge stretches away from the camera - two arches dominate the centre of the bridge, with supporting chains visible on either side.  A prominent bilingual "Road Closed" sign is positioned in the foreground of the image, with a worker in hi-vis clothing standing by some temporary fencing to the left of the sign.
The bridge was first closed in October 2022, with frequent restrictions on lorries and heavy goods vehicles alongside the use of temporary lights, since it reopened

The Welsh government's deputy minister for transport, Mark Hooper, called the new delay "unacceptable" and said he was extremely disappointed.

Disruptions on the Menai suspension bridge began in October 2022 - when the bridge closed suddenly after serious safety issues were found.

Those initials concerns were addressed, but a second phase of work - to repaint the bridge and carry out repairs to the stonework - has been ongoing since February 2025.

Officials originally said the work would be finished by August that year, but the anticipated deadline later shifted to December 2025. Since then the deadline has once again slipped - first to April 2026, then to spring 2027, and now to "autumn 2027".

Hooper had previously said he was "confident that we'll be finished for spring 2027".

Speaking on Monday, he said: "People have put up with delays and inconvenience on this bridge for too long, which is why this government has acted swiftly to get going on a third Menai crossing.

"I was extremely disappointed and frustrated to learn from the contractors that their programme of repairs, which has been beset by numerous delays, will be delayed once again.

"I have made it clear to UK Highways A55 Ltd since taking on this role, the importance of maintaining momentum and providing confidence in the delivery programme - so this latest delay is unacceptable."

Temporary traffic lights have been a regular feature on the bridge while repair work is being carried out, though they are not currently in use.

The bridge also has temporary speed bumps and a weight restriction of 7.5 tonnes, in place, and is obliged to close for safety checks if a heavy vehicle crosses.

UK Highways A55 Ltd said the latest delay followed the discovery of damp seeping through the deck to the steelwork underneath, making it difficult to paint the bridge.

A solution to the damp issue has been found, with the contractor stating it will try to minimise any future disruption to journeys by not using temporary traffic lights at busy times.

Around 30 working days were additionally lost over the summer when the weather made it too hot to work underneath the bridge.

A spokesperson said: "The bridge is a Grade I-listed, 200-year-old structure - this brings with it additional technical and design challenges.

"The principal technical issue is now understood, an appropriate solution has been identified, productive work has continued, and uncertainty around the remaining repair scope has reduced.

"The project therefore has a clearer and more credible route to completion."