City centre's £90m refurbishment gets approval
Cambridge City CouncilA multimillion-pound refurbishment of major buildings and overhaul of the market place in Cambridge city centre has been approved.
The city council has agreed to pay almost £90m to carry out work to the Guildhall, Corn Exchange and Market Square. A further £7.5m contingency fund was also approved.
Work is due to start in January and is expected to be completed by August 2029.
A council meeting on Thursday was told the local authority should recoup the money within 30 years as a result of income generated by the refurbished facilities.
The council says the work at the Guildhall is necessary to combat water damage and a deteriorating roof. The work will also make the building accessible to wheelchair users.
Last night's council meeting also heard a refurbished council chamber would be large enough to host a new unitary authority, which is expected to be formed after local government reorganisation across Cambridgeshire.
The Corn Exchange entertainment venue needs a new roof and better ventilation, and the plans aim to improve energy efficiency.
The Market Square will have more seating, lighting, access to power and better toilets.
Cambridge City CouncilThe council say the project should be finished within three years and it has produced the following timeline:
- January 2027 – start on site and enabling works begin
- January to April 2027 - subject to planning approval, Market Square traders will gradually begin to relocate to temporary city centre locations where they will continue to trade
- March 2028 - Market Square works expected to be completed
- Summer 2028 - Corn Exchange refurbishment expected to be completed
- December 2028 - Guildhall refurbishment expected to be completed
- August 2029 - wider public realm works across the Civic Quarter expected to be completed